The canal-based water supply project in Ludhiana, co-funded by the World Bank and the Asian Infrastructure Investment Bank (AIIB), has recorded an overall physical progress of 54.4% and remains on track to meet its scheduled timeline.
Reviewing the ongoing construction of the Water Treatment Plant (WTP) at Bilga village near Sahnewal, Mayor Inderjit Kaur noted steady progress across key project components—including active construction on 59 of the 70 proposed overhead water tanks and approximately 32% completion in the rehabilitation of existing tanks. The executing agency and the Project Implementation Unit (PIU) have been directed to expedite execution, uphold strict quality and safety compliance, and aim for early completion while minimising inconvenience to citizens.
News by Rahul Yelligetti.